Project Highlights
- Mill and overlay pavement on Eastern Avenue from Flamingo Road to Desert Inn Road
- Replace existing sidewalk ramps within project limits that do not meet current ADA standards
- Adjust utility valves and manholes as required to accommodate roadway paving operations
- Construct medians
- Provide defector loop infrastructure at signalized intersection approaches
- Replace damaged signs
- Add new signs
- Re-stripe roadways
Project Facts
Contractor: Las Vegas Paving
Contract Amount: $4,045,000
Construction Start: November 18, 2022
Construction Complete: December 2022
Commission District: A
Traffic Impacts
The project will include nighttime lane restrictions on Hotel Rio Drive from Flamingo Road to Dean Martin Drive, including several full closures of Hotel Rio Drive. Please text ClarkCounty to 406-201-3555 to subscribe for construction updates.
Contacts
Clark County Public Works Project Outreach Information Line: (702) 804-2199
Email: info@resortcorridor.com
Project Updates
Construction is scheduled to start on September 12, 2022. Visit our interactive map to stay updated on current and upcoming traffic restrictions.