Las Vegas Boulevard Phase B, I-215 to Mandalay Bay

Project Highlights

  • New pavement
  • Sanitary sewer line replacement
  • Water main line replacement
  • Intersection modifications for improved pedestrian crossing
  • Technology upgrades to traffic signal systems and lighting with Smart Poles
  • Enhancements to median landscaping and LED lighting

Project Facts

Contractor:  TAB Contractors
Construction Management: Horrocks Engineers
Contract Amount: $40M
Construction Duration: 450 calendar days, estimated completion Fall 2022
Construction Start: July 12, 2021
Commission District: A & G

Traffic Impacts

The project will include nighttime lane restrictions, outside lane closures, short-term left-turn and bus stop closures at various times throughout the project. Please subscribe for construction updates.
  • This project will be constructed in Phases, see the Phasing exhibit for details.
  • Construction work hours are 2 a.m. to 10 a.m. Monday-Friday.
  • Lane restrictions are anticipated to start on July 12th at approximately 12:30 a.m.
    > Traffic Control set-up will start roughly 1 ½ hours prior to construction start time, and removed within 1 hour of construction end time.
  • The anticipated duration for construction in Phase 1W is 7-10 weeks*.
  • Business access will be maintained during construction.

*Construction schedule is subject to change.

Contacts

Urgent Construction Concerns: (702) 642-3623
  • Construction Hours: Mathew Barber
  • Non-construction Hours: Taylor Bernard
Email Questions to: lvbri@nclasvegas.com

CCPW Construction Representative: Lee Jacoby (435) 574-7737

Sign-Up to Receive Important Updates!

We'll keep you informed about traffic updates and lane restrictions surrounding The Resort Corridor Projects. * Standard text message rates may apply